The Process

We have provided an outline of here for what you can expect throughout your build. 

Although each job will vary a little, but this gives you an idea of the process.

We keep you updated throughout every step of your project.

WEEK 1

Erection of scaffold.

Delivery of skip and materials.

Board out scaffold for safety.

​

WEEK 4

Internal Electrics.

Plumbing.

Insulation.

​

​

​

WEEK 7

Plastering.

Interior Carpentry

​

​

​

WEEK 2

Delivery and installation of structural still beam.

​

​

WEEK 5

Breaking through to existing property & installation of new staircase.

Installation of window and floor roof lights.

​

WEEK 8

Final installation of electrics and heating.

Installation of bathroom suite.

​

​

WEEK 3

Installation of floor construction of roof and rear dormer.

​

​

WEEK 6

Fitting of exterior roof tiles.

​

​

​

​

​

WEEK 9

Completion and final inspection from building control.

​

​

​